A conceptual framework of the interface between the design and construction processes

Download (219.79 kB)
journal contribution
posted on 2023-08-30, 13:56 authored by Adrian Mitchell, Ian Frame, Alan Coday, Mike Hoxley
Purpose – As the construction industry strives for closer integration of the participants, more responsibility for the management of the detailed design process is being directed to main contractors and combined with their existing duties of managing the construction and pre-construction processes. Crucially, this necessitates successful management of the interface between these processes, and this paper seeks to investigate a conceptual view of that interface to provide a foundation for improving understanding of it. Design/methodology/approach – Recent and current literature is examined, and various theoretical backgrounds for the design and the construction processes are reviewed. The consequences for the understanding of the interface are discussed. The significance of conceptual frameworks is also reviewed. Findings – A significant difference is identified in the published work between the theoretical understandings of the construction and design processes. From this a conceptual framework for the interface between these processes is developed. Practical implications – The difference identified may have significant implications for further research, and for the development of management techniques applicable to the interface. Furthermore, the lack of access to specialist knowledge at the optimum time during the design process is identified as having a potentially significant impact on that process. Originality/value – These findings could provide an understanding and basis for further research into the interface between the processes, and for the development of an enhanced model that would facilitate improved management of the interface and the optimisation of the process of the selection, appointment and input of specialist subcontractors.

History

Refereed

  • Yes

Volume

18

Issue number

3

Page range

297-311

Publication title

Engineering, Construction and Architectural Management

ISSN

1365-232X

Publisher

Emerald

File version

  • Accepted version

Language

  • eng

Legacy posted date

2013-12-24

Legacy creation date

2020-03-24

Legacy Faculty/School/Department

ARCHIVED Faculty of Science & Technology (until September 2018)

Usage metrics

    ARU Outputs

    Categories

    No categories selected

    Exports

    RefWorks
    BibTeX
    Ref. manager
    Endnote
    DataCite
    NLM
    DC